$183 439,00

Budget for the project action

Reconstruction of the village sewer pipe in Speia

Localities:

  • Level: Local
  • Region: Center
  • District: Anenii Noi
  • Locality: Speia

Contributing partners:

$183 439,00

SDG
SDG

Focus Areas:

  • Citizen engagement
  • Capacity development
  • Confidence building

Target groups:

  • Local authorities
  • Population

Timeline:

Start date End date
01 Oct 2016 01 Aug 2017

Results:

  • Connection of kindergarten, 5 floors-high buildings and the high school to the main pipeline of the sewerage system
  • Construction of the sewerage pressure pipeline between pumping and waste treatment stations
  • The waste treatment station was purchased and is installed

Beneficiaries:

  • 3,271 (village population: 1,720 women and 1,550 men)